Project was tendered March 2016, awarded March 2016 and completed June 2016.
The project included the following:
- Supply & installation of the cable ladder system.
- Supply & installation of the electrical, instrumentation & communication cabling.
- Supply & installation of the light, power & new distribution board.
- Installation of new VSD’s, PLC modifications & MCC upgrades.
- Dry and Wet testing and commissioning.